Net Present Value (NPV) and Internal Rate of Return (IRR)

Net Present Value (NPV) and Internal Rate of Return (IRR)


Several important decision-making criteria are used to evaluate capital investments. The two most comprehensive and well-understood measures of whether or not a project is profitable are the net present value (NPV) and the internal rate of return (IRR). Other measures include the payback period, discounted payback period, average accounting rate of return (AAR), and the profitability index (PI).

Net Present Value (NPV)

The net present value (NPV)  of a project is the potential change attributed to a project after accounting for the time value of money. The NPV for a project with one investment outlay made at its initiation is defined as the present value of the future after-tax cash flows minus the investment outlay.

$$ \mathrm{NPV}=\sum_{t=1}^{n} \frac{C F_{t}}{(1+r)^{t}} \text { – Outlay } $$

Where:

\(CF_t\) = After-tax cash flow at time \(t\).

\(r\) = Required rate of return for the investment.

\(\text{Outlay}\) = Investment cash flow at time zero.

Many projects have cash flow patterns in which outflows not only occur at the time of initiation (at time = 0) but also at future dates. In these instances, a better formula to use is:

  • To invest in the project if NPV > 0.
  • Not to invest in the project if NPV < 0.
  • Stay indifferent if NPV = 0.

In other words, positive NPV investments are wealth increasing, while negative NPV investments are wealth decreasing.

Example: Net Present Value of a Project

Assume that Company A is considering an investment of $100 million in a capital expansion project that will return after-tax cash flows of $20 million per year for the first 3 years and another $33 million in year 4, the final year of the project. If the required rate of return for the project is 8%, what would the NPV be, and should the company undertake this project?

$$
\begin{aligned}
\mathrm{NPV} &=\frac{20}{1.08^{1}}+\frac{20}{1.08^{2}}+\frac{20}{1.08^{3}}+\frac{33}{1.08^{4}}-100 \\
&=18.519+17.147+15.877+24.256-100 \\
&=-\$ 24.201 \text { million }
\end{aligned}

$$

Since the NPV < 0, the project should not be undertaken.

Internal Rate of Return

The internal rate of return (IRR) is the discount rate that makes the net present value (NPV) of all cash flows from a particular project equal to zero. For a project with one initial outlay, the IRR is the discount rate that makes the present value of the future after-tax cash flows equal to the investment outlay.

The IRR solves the equation:

$$ \sum_{t=1}^{n} \frac{C F_{t}}{(1+I R R)^{t}}-\text { Outlay }=0 $$

It looks very much like the NPV equation, except that the discount rate is the IRR instead of \(r\), the required rate of return. Discounted at the IRR, the NPV is equal to zero.

The decision rule for the IRR is:

  • To invest in the project if the IRR exceeds the required rate of return for the project, i.e., invest if IRR > \(r\).
  • Not to invest if IRR < \(r\).

In instances where the outlays for a project occur at times other than time 0, a more general form of the IRR equation is:

$$ \sum_{t=0}^{n} \frac{C F_{t}}{(1+I R R)^{t}}=0 $$

Example: IRR of a Project

Here is a follow-up on the above NPV example. Assume that Company A is considering an investment of $100 million in a capital expansion project that will return after-tax cash flows of $20 million per year for the first 3 years and another $33 million in year 4, the final year of the project. What is the IRR for this project, and should it be undertaken given that the required rate of return for the project is 8%?

Solve IRR in the following equation:

$$ -100+\frac{20}{(1+I R R)^{1}}+\frac{20}{(1+I R R)^{2}}+\frac{20}{(1+I R R)^{3}}+\frac{33}{(1+I R R)^{4}}=0 $$

The solution can be arrived at through trial and error. However, a simpler approach is to use a financial calculator:

Step 1: Entering the Initial Cash Outlay

Press the Cash Flow [CF] key to open the cash flow register. The calculator should read CF0=, which tells you to enter the cash flow for time 0. Since you need to send cash out of the company to make the initial $100 investment, this value has to be negative. Key in -100 for CF0, and hit the [ENTER] key.

Step 2: Entering the Cash Inflows

Next, enter the cash flow values for the subsequent periods. This is done by hitting the down arrow once. The calculator should read CF1=. Type in the amount for the first cash flow, 20, and hit [ENTER]. The calculator should now say C01=20.

To enter cash flow from Year 2, hit the down arrow twice. The calculator should read CF2=. If it says F1=, hit the down arrow one more time.

Type in the second year’s cash flow, 20, and hit [Enter]. The calculator should read CF2=20. Hit the down arrow twice, again, and do the same for the third cash flow period, CF3.

Do this once more and for the last time to enter the last cash flow, 33.

Step 3: Calculating the IRR

Once the cash flow values have been fed into the calculator, you are ready to calculate the IRR.

To do this, press the [IRR] key. The screen will read IRR=0.000. To display the IRR value for the data set, press the [CPT] key at the top left corner of the calculator. If you have followed this process correctly, the calculator will display the correct IRR. The IRR is computed to be -2.626%. Since -2.626% < 8%, the project should not be undertaken.

Simply computing a project’s NPV and IRR to determine which of several projects to undertake is not always as straightforward. The IRR and NPV can produce different ranking outcomes whenever mutually exclusive projects are involved. Nevertheless, other challenges may occur.

Graphical Illustration

The NPV Profile illustrates a project’s NPV graphed as a function of various discount rates. The NPV values are graphed on the vertical or y-axis, while the discount rates are graphed on the horizontal or x-axis.

  • The graph crosses the y-axis (vertical axis) when the discount rate = 0%.
  • The graph crosses the x-axis (horizontal axis) when the NPV = 0 and the discount rate is the IRR.

NPV and IRR Comparison

For independent, conventional projects, the decision rules for the NPV and IRR will both draw the same conclusion on whether to invest or not. However, in the case of two mutually exclusive projects, the decision rules will sometimes draw different conclusions. For example, project X might have a larger NPV than project Y, but project Y might have a larger IRR. This conflict usually stems from differences in the cash flows of the two projects, which leads to a different ranking between the NPV and IRR. Whenever this conflict arises, the NPV, not the IRR, should be used to select the project to invest in.

Another circumstance that may cause mutually exclusive projects to be ranked differently according to NPV and IRR criteria is the scale or size of the project.

Multiple IRR and No IRR Problem

Although rare, a project may have more than one IRR or no IRR at all. However, multiple IRRs cannot occur for conventional projects with cash outlay followed by cash inflows. Still, they may occur for non-conventional projects with cash flows that change signs (negative, positive) more than once during a project’s life.

The net present value (NPV) and the internal rate of return (IRR) are both techniques that financial institutions or individuals can use when they are making major investment decisions. Each method has its strengths and weaknesses. However, the net present value method comes out on top, and here’s why. Both NPV and IRR will yield the same investment decisions when dealing with independent projects. By independent, we mean that deciding to invest in one project does not rule out or affect investment in another project.

However, a challenge arises when projects are mutually exclusive. If two or more projects are mutually exclusive, the decision to invest in one project precludes investment in all the others. With such projects, the IRR method may provide misleading results if used in isolation.

Shortcomings of IRR

As seen, there are some problems associated with the IRR method:

  • The method assumes that all proceeds from a project are immediately reinvested in projects, offering a rate of return equal to the IRR – this is very difficult in practice.
  • It gives different rankings when the projects under comparison have different scales.
  • Sometimes, the method may not provide a unique solution. This, especially, happens when a project has a mixture of positive and negative cash flows during its productive life.

Question 1

You have been provided with the following cash flows for a capital project:

$$ \begin{array}{c|c|c|c|c|c|c}
\text { Year } & 0 & 1 & 2 & 3 & 4 & 5 \\
\hline \text { Cash flow }(\$) & -50,000 & 10,000 & 10,000 & 15,000 & 15,000 & 15,000
\end{array} $$

Given a required rate of return of 8 percent, the NPV and IRR of the project are closest to:

  1. NPV: $1,023; IRR: 10.64%.
  2. NPV: $974; IRR: 8.68%.
  3. NPV: $2,400; IRR: 7.12%.

Solution

The correct answer is B.

$$ \begin{aligned}
\text{NPV}&=-50,000+\frac{10,000}{1.08^{1}}+\frac{10,000}{1.08^{2}}+\frac{15,000}{1.08^{3}}+\frac{15,000}{1.08^{4}}+\frac{15,000}{1.08^{5}} \\
&=-50,000+9259.26+8573.39+11,907.48++11,025.45+10,208.75 \\
&=\$ 974.33 \text { million }
\end{aligned} $$

Question 2

In an NPV profile, the point at which the profile crosses the x-axis is best described as:

  1. The project’s IRR.
  2. The point at which the NPV is highest.
  3. The point at which the discount rate = 0% and the NPV is the sum of the undiscounted cash flows for the project.

Solution

The correct answer is A.

At the horizontal axis, the NPV = 0, and by definition, this occurs whenever the discount rate is the IRR.

Question 3

Suppose you have three independent projects – X, Y, and Z. Assume that the hurdle rate is 12% for all the three projects. Their NPVs and IRRs are as shown below.

$$ \begin{array}{c|c|c|c}
& \textbf { Project X } & \textbf { Project Y } & \textbf { Project Z } \\
\hline \text { NPV } & \$ 20,000 & \$ 21,400 & \$ 23,000 \\
\text { IRR } & 20 \% & 32 \% & 18 \%
\end{array} $$

Assuming the projects are mutually exclusive, which of the following is the most economically feasible project?

  1. Z.
  2. X.
  3. Y.

Solution

The correct answer is A.

$$
\begin{array}{c|c|c|c}
& \textbf { Project } \mathbf{X} & \textbf { Project Y } & \textbf { Project } \mathbf{Z} \\
\hline \text { NPV } & \$ 20,000 & \$ 21,400 & \$ 23,000 \\
\text { IRR } & 20 \% & 32 \% & 18 \% \\
\text { Decision } & \text { Accept } & \text { Accept } & \text { Accept }
\end{array}
$$

If the IRR criterion is used, all the three projects would be accepted because they would all increase shareholders’ wealth. Their NPVs are all positive and, again, the three are all acceptable.

However, if the projects are mutually exclusive, then, only one project would be chosen. If one were to pick one project based on internal rates of return of the projects, then one would go for Y. This is because its IRR is the highest compared to the other projects.

This decision would be wrong when we consider the sizes of the NPVs of the projects. While Y has the highest IRR, its NPV is lower than that of Z. The best decision would be to go for the project with the highest NPV, and that is project Z. Therefore, if projects are mutually exclusive, the NPV method should be applied.

Shop CFA® Exam Prep

Offered by AnalystPrep

Featured Shop FRM® Exam Prep Learn with Us

    Subscribe to our newsletter and keep up with the latest and greatest tips for success

    Shop Actuarial Exams Prep Shop Graduate Admission Exam Prep


    Sergio Torrico
    Sergio Torrico
    2021-07-23
    Excelente para el FRM 2 Escribo esta revisión en español para los hispanohablantes, soy de Bolivia, y utilicé AnalystPrep para dudas y consultas sobre mi preparación para el FRM nivel 2 (lo tomé una sola vez y aprobé muy bien), siempre tuve un soporte claro, directo y rápido, el material sale rápido cuando hay cambios en el temario de GARP, y los ejercicios y exámenes son muy útiles para practicar.
    diana
    diana
    2021-07-17
    So helpful. I have been using the videos to prepare for the CFA Level II exam. The videos signpost the reading contents, explain the concepts and provide additional context for specific concepts. The fun light-hearted analogies are also a welcome break to some very dry content. I usually watch the videos before going into more in-depth reading and they are a good way to avoid being overwhelmed by the sheer volume of content when you look at the readings.
    Kriti Dhawan
    Kriti Dhawan
    2021-07-16
    A great curriculum provider. James sir explains the concept so well that rather than memorising it, you tend to intuitively understand and absorb them. Thank you ! Grateful I saw this at the right time for my CFA prep.
    nikhil kumar
    nikhil kumar
    2021-06-28
    Very well explained and gives a great insight about topics in a very short time. Glad to have found Professor Forjan's lectures.
    Marwan
    Marwan
    2021-06-22
    Great support throughout the course by the team, did not feel neglected
    Benjamin anonymous
    Benjamin anonymous
    2021-05-10
    I loved using AnalystPrep for FRM. QBank is huge, videos are great. Would recommend to a friend
    Daniel Glyn
    Daniel Glyn
    2021-03-24
    I have finished my FRM1 thanks to AnalystPrep. And now using AnalystPrep for my FRM2 preparation. Professor Forjan is brilliant. He gives such good explanations and analogies. And more than anything makes learning fun. A big thank you to Analystprep and Professor Forjan. 5 stars all the way!
    michael walshe
    michael walshe
    2021-03-18
    Professor James' videos are excellent for understanding the underlying theories behind financial engineering / financial analysis. The AnalystPrep videos were better than any of the others that I searched through on YouTube for providing a clear explanation of some concepts, such as Portfolio theory, CAPM, and Arbitrage Pricing theory. Watching these cleared up many of the unclarities I had in my head. Highly recommended.